~6,000 m³
Stage 1 in-situ
~4,000 m³
Stage 2 in-situ
SA EPA
flocculant compliance

South Australia
Port Dredging — Sediment Dewatering
The Challenges
Maintenance dredging at the Port of Adelaide produced sediment that had to be dewatered on a tight wharf footprint and managed within EPA marine-discharge requirements.
Our Approach
Feasibility and containment-cell layout, extensive flocculant selection and dosing guidance to satisfy the EPA, and on-site inspections through filling.
Results
Two stages — about 10,000 m³ of in-situ dredged material — were dewatered into stackable cake of broadly similar volume within the lined, bunded cell.